External and regular users on all account types can create milestones.
⏱ 1 min read
Milestones are tasks that are scheduled for one day and have no duration. Milestones are used as reference points to mark a major event or a branching decision point in a project.
You can convert any existing task into milestone:
Alternatively, right-click a task in the List view and select “Convert to milestone” from the menu that appears.
If no start/end dates are selected before the task is converted into milestone with a current date as a due date. If the end date was specified it becomes the due date for the milestone.
Wrike Tip! One more way to convert a task into a milestone from the Task view:
Milestone tasks are displayed as a diamond symbol 1 on the Gantt Chart.
To create a milestone on the Gantt Chart:
The milestone is created and you can add any additional information to it.